The work included complete EPC of 2MW Rooftop solar PV System with SCADA and Intelligent Synchronization with Grid and DG.
63KV / 20KV, 25MVA Hybrid substation
LOCATION : EAST AFRICA
The work included complete EPC and 63KV UG Cable for LILO, connecting to country utility substation with all approvals, Protection System, and SCADA Integration.
20KV / 415V, 1.25MVA Unit substation - 7 Nos
LOCATION : EAST AFRICA
The work included complete EPC and 5Kms 20KV UG Cable for Ring feeder arrangements connecting to 63KV / 20KV with all approvals, Protection System, and SCADA Integration.
DG SYNCHRONIZATION PANEL
LOCATION : EAST AFRICA
The work included Engineering, supply, erection and commissioning of 1600 Amps ACB Panel with DEIF controller – 6Nos, 6300 Amps ACB Panel – 1No, 2500 Amps ACB Panel – 1No, 1000A MCCB Panel -2 Nos,
1 x 4MVA, 11KV / 0.415KV Transformer with all approvals, Protection System and SCADA Integration.
Solar Pump for Desert farming
LOCATION : EAST AFRICA
The work included Engineering, supply ,erection and commissioning of 2 sets for 4 nos of deep borewell of each 150m depth with 18KW off-grid solar power plant.